Eversole Run Middle School, Dublin City Schools

At Triad, we work to bring community aspirations to life. We value your vision and strive to build and care for the community you live in and leave for future generations.

  • Project Completion

    2021

  • Construction Cost

    $45 million

  • Client Contact

    Jeff Stark, Chief of Operations 614.764.5913

The Call: A New Middle School Connected to a New Elementary School, Both Under Construction at Once

Dublin City Schools was building Eversole Run Middle School attached to the Abraham Depp Elementary School campus. The two schools would share a kitchen and cafeteria, creating operational efficiencies that justified the connected design. But both buildings were under construction simultaneously, each managed by a separate construction manager. The point where the two structures connected was the project’s most critical coordination challenge. A building envelope tie-in between two structures being built by two different teams had to be executed precisely. If the connection failed, both buildings would be affected for their entire lifespan.

Choosing a Partner to Own the Connection Point

When two construction teams are building two connected structures simultaneously, the risk lives at the seam. Neither team fully owns the connection point by default. The coordination required to get it right depends on someone taking responsibility for ensuring both sides meet precisely. The district needed a partner with deep expertise in building envelope design and the ability to coordinate across two construction teams. They chose Triad.

The Decisions That Made the Seam the Strongest Point on Campus

The shared services between the elementary and middle school had to be programmed carefully. A shared kitchen and cafeteria serving both elementary and middle school students required thoughtful scheduling, circulation design, and spatial planning to ensure the shared spaces worked for both grade levels without creating conflicts.

The building envelope tie-in was the project’s defining technical challenge. Both buildings were going up simultaneously. Two construction managers. Two schedules. Two teams. And one connection point where the building envelopes had to meet seamlessly. Triad took responsibility for the tie-in, producing detailed documentation that specified exactly how the two structures would connect. Clear communication was maintained between both construction teams throughout. And ongoing oversight verified that the connection was executed as designed.

Beyond the tie-in, Triad designed the building envelope for the entire Eversole Run Middle School. The envelope had to integrate seamlessly with the elementary school at the connection point while performing independently everywhere else. The design ensures long-term protection and energy efficiency for the middle school.

Two Connected Schools Where the Seam Is the Strongest Point

Eversole Run Middle School and Abraham Depp Elementary School are now connected on a shared campus. A shared kitchen and cafeteria serve both grade levels. The building envelope tie-in was coordinated precisely between two construction teams, with Triad owning the connection point through detailed documentation, clear communication, and ongoing oversight. The middle school envelope was designed for high performance. The project was delivered on schedule despite the complexity. And the point where the two buildings meet, the place where the coordination could have failed, is instead the strongest proof that it worked.